Exponentially smoothed forecast for period 8
1. In period 7 the exponentially smoothed forecast was 50 and the actual demand was 49. If alpha is equal to 0.10, what is the exponentially smoothed forecast for period 8? 2. Number of hours required per unit is 4 hours and there are 8 working hours per day. There are 20 working days in each month. Find the number of workers