CPM, problem : Minimum cost schedule, Crashing
Not what you're looking for?
Information concerning a project is given below. Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 14.
a) What is the project's duration if only normal times are used?
b) What is the minimum-cost schedule?
c) What is the critical path for the minimum-cost schedule?
Activity Normal Normal Cost Crash time crash cost immediate Predecessor
Time ($) (days) ($)
A 5 1,000 4 1,200 ---
B 5 800 3 2,000 -----
C 2 600 1 900 A,B
D 3 1,500 2 2,000 B
E 5 900 3 1,200 C,D
F 2 1,300 1 1,400 E
G 3 900 3 900 E
H 5 500 3 900 G
Purchase this Solution
Solution Summary
This posting contains solution to following CPM Crashing problem.
Purchase this Solution
Free BrainMass Quizzes
Geometry - Real Life Application Problems
Understanding of how geometry applies to in real-world contexts
Know Your Linear Equations
Each question is a choice-summary multiple choice question that will present you with a linear equation and then make 4 statements about that equation. You must determine which of the 4 statements are true (if any) in regards to the equation.
Solving quadratic inequalities
This quiz test you on how well you are familiar with solving quadratic inequalities.
Probability Quiz
Some questions on probability
Exponential Expressions
In this quiz, you will have a chance to practice basic terminology of exponential expressions and how to evaluate them.