    CPM, problem : Minimum cost schedule, Crashing

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Information concerning a project is given below. Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 14.
    a) What is the project's duration if only normal times are used?
    b) What is the minimum-cost schedule?
    c) What is the critical path for the minimum-cost schedule?

    Activity Normal Normal Cost Crash time crash cost immediate Predecessor
    Time ($) (days) ($)

    A 5 1,000 4 1,200 ---
    B 5 800 3 2,000 -----
    C 2 600 1 900 A,B
    D 3 1,500 2 2,000 B
    E 5 900 3 1,200 C,D
    F 2 1,300 1 1,400 E
    G 3 900 3 900 E
    H 5 500 3 900 G

    © BrainMass Inc. brainmass.com October 9, 2019, 6:59 pm ad1c9bdddf
    https://brainmass.com/math/optimization/cpm-problem-minimum-cost-schedule-crashing-104318

    Solution Summary

    This posting contains solution to following CPM Crashing problem.