The data for a Time-Cost CPM Scheduling model analysis are given below. The times are in days. What is the minimum cost to complete this project in 14 days? (Hint: This problem requires crashing).

Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash cost
A None 4 2 2000 4000
B A 4 3 3000 6000
C A 2 1 2000 2500
D B and C 4 2 5000 5600
E D 3 1 6000 9000

Purchase this Solution

Solution Summary

Solution analyzes the given CPM problem and calculates the minimum cost to complete the project in 14 days.

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.

Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.

Basics of corporate finance

These questions will test you on your knowledge of finance.