    Time-Cost CPM Scheduling Model

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    The data for a Time-Cost CPM Scheduling model analysis are given below. The times are in days. What is the minimum cost to complete this project in 14 days? (Hint: This problem requires crashing).

    Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash cost
    A None 4 2 2000 4000
    B A 4 3 3000 6000
    C A 2 1 2000 2500
    D B and C 4 2 5000 5600
    E D 3 1 6000 9000