Explore BrainMass
Share

Explore BrainMass

    Quantitative Analysis: PERT/CPM Case Study

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    For an organization, the following project schedule is given.Assume that all times are in days.

    Task Predecessor Normal Time Crash Time Crash cost Slope

    A NONE 7 7 NA

    B A 3 3 NA

    C A 8 4 600

    D A 4 4 NA

    E B 6 5 600

    F C, D 2 2 NA

    G E, F 6 6 NA

    H F 5 3 400

    I G, H 4 4 NA

    J I 2 2 NA

    In a 3 to 4 page Microsoft Word document, address the following:

    Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

    © BrainMass Inc. brainmass.com April 4, 2020, 1:08 am ad1c9bdddf
    https://brainmass.com/business/project-management/quantitative-analysis-pert-cpm-case-study-593427

    Solution Summary

    The problem set deals with questions about crashing a project duration.

    $2.19

    ADVERTISEMENT