Explore BrainMass
Share

Explore BrainMass

    Quantitative analysis:Networks, PERT, critical path.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    1. Develop a network drawing for Hill Construction & determine the critical path. How long is the project expected to take?
    2. What is the probability of finishing in 270 days?
    3. If it's necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.

    © BrainMass Inc. brainmass.com May 20, 2020, 7:34 pm ad1c9bdddf
    https://brainmass.com/business/project-management/quantitative-analysis-networks-pert-critical-path-344985

    Attachments

    Solution Summary

    The problem set deals with estimating project duration through PERT/CPM techniques.

    $2.19

    ADVERTISEMENT