Explore BrainMass
Share

Applied Quantitative Medthods and PERT network

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

Construct a PERT network and answer each of the following questions using the table attached. (table represents a project to convert a 20-bed unit in a nursing home to accommodate patients with dementia)

a) What is the expected project completion date?
b) What is the scheduled start and completion date for each activity?
c) Which activities are on the critical path?
d) How long can noncritical path activities be delayed without jeopardizing the overall completion date for this project?

© BrainMass Inc. brainmass.com October 25, 2018, 8:07 am ad1c9bdddf
https://brainmass.com/health-sciences/topics-in-health-and-wellness/applied-quantitative-medthods-and-pert-network-526862

Attachments

Solution Summary

A six page long, step by step explanation of PERT network critical path solution for an effective project management

$2.19