Quantitative analysis:Networks, PERT, critical path.
Not what you're looking for?
The following data were obtained from an in-house MIS project:
Activity Duration Predecessors
A 3 Days ---
B 6 Days ---
C 3 Days A
D 2 Days B
E 3 Days B
F 1 Day C, D
G 5 Days C, D
H 4 Days E, F, G
I 7 Days E, F
Construct a network for the project. Then review and answer (A) and (B).
(A.) Calculate the scheduled completion time and identify the critical path.
(B.) What is the slack time (float) for activities A, D, E, and F?
Purchase this Solution
Solution Summary
The problem set deals with issues in Quantitative analysis: Critical path, slack and project completion using PERT techniques.
Solution Preview
PROBLEM 4
The following data were obtained from an in-house MIS project:
Activity Duration (Days) Predecessors
A 3
B 6
C 3 A
D 2 B
E 3 B
F 1 C, ...
Education
- B. Sc., University of Nigeria
- M. Sc., London South Bank University
Recent Feedback
- "Thank you."
- "thank you Chidi Ngene.. if you have any APA references would be great"
- "Thank you so much for your help, your explanations were easy to understand and apply!"
- "are you able to highlight the equations used either on the xlsx or a word doc as to how each graph was formed- overall looks fine i just need help understanding this myself"
- "Chidi Ngene, M. Sc. Was extremely helpful as without the help and guidance I would have failed, but with the help I passed. I still have a lot to learn and in need of the guidance to understand and learn more on the subject. I would recommend Chidi Ngene and BrainMass to anyone that are in need of help. Thank you!!"
Purchase this Solution
Free BrainMass Quizzes
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.
Operations Management
This quiz tests a student's knowledge about Operations Management
Understanding the Accounting Equation
These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.
Writing Business Plans
This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.
MS Word 2010-Tricky Features
These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.