Quantitative analysis:Networks, PERT, critical path.

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

Solve the following CPM/PERT Network Analysis problem:
Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 27 days or less.

Time Estimates (Days)
Activity a m b
1 5 8 15
2 7 10 12
3 3 5 6
4 1 3 6
5 4 6 7
6 3 3 3
7 3 4 6

© BrainMass Inc. brainmass.com October 25, 2018, 3:40 am ad1c9bdddf
https://brainmass.com/statistics/analysis-of-variance/quantitative-analysis-networks-pert-critical-path-349015

Attachments

Solution Summary

The problem deals with topics under quantitative analysis. It deals with determining project duration, probability of completion through critical path methods and program evaluation and review technique.

$2.19
See Also This Related BrainMass Solution

Quantitative analysis: Networks, PERT, critical path...

The following data were obtained from an in-house MIS project:

Activity Duration Predecessors
A 3 Days ---
B 6 Days ---
C 3 Days A
D 2 Days B
E 3 Days B
F 1 Day C, D
G 5 Days C, D
H 4 Days E, F, G
I 7 Days E, F

Construct a network for the project. Then review and answer (A) and (B).

(A.) Calculate the scheduled completion time and identify the critical path.

(B.) What is the slack time (float) for activities A, D, E, and F?