    Quantitative analysis:Networks, PERT, critical path.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Solve the following CPM/PERT Network Analysis problem:
    Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 27 days or less.

    Time Estimates (Days)
    Activity a m b
    1 5 8 15
    2 7 10 12
    3 3 5 6
    4 1 3 6
    5 4 6 7
    6 3 3 3
    7 3 4 6

    © BrainMass Inc. brainmass.com October 2, 2020, 12:50 am ad1c9bdddf
    https://brainmass.com/statistics/analysis-of-variance/quantitative-analysis-networks-pert-critical-path-349015

    Attachments

    Solution Summary

    The problem deals with topics under quantitative analysis. It deals with determining project duration, probability of completion through critical path methods and program evaluation and review technique.