Share
Explore BrainMass

Quantitative analysis:Networks, PERT, critical path.

Solve the following CPM/PERT Network Analysis problem:
Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 27 days or less.

Time Estimates (Days)
Activity a m b
1 5 8 15
2 7 10 12
3 3 5 6
4 1 3 6
5 4 6 7
6 3 3 3
7 3 4 6

Attachments

Solution Summary

The problem deals with topics under quantitative analysis. It deals with determining project duration, probability of completion through critical path methods and program evaluation and review technique.

$2.19