    Identify the first activity to be crashed on a CPM network

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.

    Activity: One
    Normal Time: 8 days
    Normal Cost: $6,000
    Crash Time: 6 days
    Crash Cost $6,800

    Activity: Two
    Normal Time: 10 days
    Normal Cost: $4,000
    Crash Time: 9 days
    Crash Cost: $5,000

    To cut one day from the project's duration, activity _____ should be crashed first, adding_______ to projects cost.

    © BrainMass Inc. brainmass.com May 20, 2020, 8:57 pm ad1c9bdddf
    https://brainmass.com/business/business-management/identify-first-activity-crashed-cpm-network-428005

    Solution Preview

    Calculate the cost of crashing per day for all the possible crashing activities on the critical path.

    Activity: One
    Normal Time: 8 days
    Normal Cost: $6,000
    Crash Time: 6 days ...

    Solution Summary

    This post explains in simple terms how to identify the candidate activity for crashing on a CPM network