    Project Evaluation Review Technique / Critical Path Method : Network, Critical Path and Analysis of Crash Activity

    Not what you're looking for? Search our solutions OR ask your own Custom question.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Please refer to the attached file for this PERT / CPM problem: I've determined that the critical path for this network is A - E - F and the project completion time is 22 weeks.

    Here's where I need help: If a deadline of 17 weeks is imposed, what activities should be crashed?

    © BrainMass Inc. brainmass.com March 4, 2021, 6:25 pm ad1c9bdddf
    https://brainmass.com/math/real-analysis/project-evaluation-review-technique-and-critical-path-method-44331

    Attachments

    Solution Preview

    Please see the attached file for the complete solution.
    Thanks for using BrainMass.

    I've determined that the critical path for this network is A - E - F and the project
    completion time is 22 weeks.
    Here's where I need help: If a deadline of 17 weeks is imposed, what activities
    should be crashed?

    Activity Normal time Crash Time Normal cost Crash cost
    A 12 8 8000 12000
    B 14 10 5000 7500
    C 8 8 10000 10000
    D 5 3 6000 8000
    E 4 3 5000 7000
    F 6 5 9000 12000
    G 10 8 5000 8000
    Listing all paths with the durations:

    Path Expected weeks
    A-D 17
    A-E-F 22
    B-F 20
    C-F 14
    C-G 18

    Since A-E-F is the path with longest duration, it is the critical path.
    To complete the project within 17 weeks, we need to crash the activity on critical path, so we should crash A, or E or F.
    1) We select activity E since its crash cost is the cheapest ($7000) among the three activities, and crash E from 4 to 3. ...

    Solution Summary

    A PERT / CPM problem is solved. Crash analysis is performed. The solution is detailed and well presented.