Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below.

Activity Normal Time Crash Time Normal Cost Crash Cost Immediate Predecessor
A 4 3 2,000 2,600 -
B 5 3 2,200 2,800 -
C 3 3 500 500 -
D 8 4 2,400 2,600 A
E 6 3 900 1,200 B
F 3 2 3,000 4,200 C
G 4 2 1,700 2,000 D,E

(a) If you wish to reduce the time required to complete this project by two weeks, which activity(ies) should be crashed, and how much will this increase the total cost?
(b) What would be the added cost if you wanted to complete the project in the minimum time possible?

Purchase this Solution

Solution Summary

The solution the software development project management and the time required to complete this project.

Purchase this Solution


Free BrainMass Quizzes
Lean your Process

This quiz will help you understand the basic concepts of Lean.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations

IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Marketing Research and Forecasting

The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.