You ask subordinates how it will take to complete the job they are working on. The subordinates say, "if everything goes right it will take 6 hours, most likely it will take 8 hours, and if everything goes wrong it will until the end of tomorrow or another 16 hours." Since this job is a part of a larger project you must estimate the expected time it will to complete the job. Using Three Activity Time estimation procedure for CPM, what is Expected Time for the job?