    Quantitative Method: Word Problem

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    You ask subordinates how it will take to complete the job they are working on. The subordinates say, "if everything goes right it will take 6 hours, most likely it will take 8 hours, and if everything goes wrong it will until the end of tomorrow or another 16 hours." Since this job is a part of a larger project you must estimate the expected time it will to complete the job. Using Three Activity Time estimation procedure for CPM, what is Expected Time for the job?

    © BrainMass Inc. brainmass.com May 20, 2020, 9:47 pm ad1c9bdddf
    https://brainmass.com/math/finite-element-method/quantitative-method-word-problem-477980

    Solution Summary

    This solution provides a detailed, step-by-step explanation of the discrete math given problem.