Setting up costs in Microsoft Project 2000 for project management: include costs?

Not what you're looking for?

Ask Custom Question

Microsoft Project 2000 has templates that can be used for getting started in project management. These are good but unfortunately, these templates don't include costs (such as hourly and overtime rates) for resources allocated.

How can I include costs?

Purchase this Solution

Solution Summary

The solution explains two ways to set up standard and overtime hourly rates in Microsoft Project. The explanation includes the details of exactly how to accomplish it.

Solution Preview

I don't believe you need a template for this. There are two ways to set up standard and overtime hourly rates in Project.

The first way is to set default rates for all resources as follows:

1. On the Tools menu option select Options and then click the General tab.
2. In the Default standard rate box enter the new hourly standard rate
3. In the Default overtime rate box, enter the new hourly overtime rate.
4. Click the "Set as Default" box
...

Purchase this Solution


Free BrainMass Quizzes
Employee Orientation

Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Motivation

This tests some key elements of major motivation theories.

Basics of corporate finance

These questions will test you on your knowledge of finance.

Team Development Strategies

This quiz will assess your knowledge of team-building processes, learning styles, and leadership methods. Team development is essential to creating and maintaining high performing teams.