Project completion and critical path, the attached file including diagram.
Not what you're looking for?
Project completion and critical path, the attached file including diagram.
Problem
(see attached)
Activity Mean Duration (Days) Std. Dev. (Days)
A 11 0.9
B 13 1.1
C 7 0.2
D 9 0.8
E 6 1
F 7 1.2
G 10 0.7
H 9 0.6
I 8 0.8
a) Calculate the project completion time.
b) Indicate the critical path activities.
c) What is the probability of completing this project between 38 and 40 days?
d) What are the slack values for activities C and F? Interpret the meaning of their slack values?
Purchase this Solution
Solution Summary
Computations shown for you in detail.
Purchase this Solution
Free BrainMass Quizzes
Employee Orientation
Test your knowledge of employee orientation with this fun and informative quiz. This quiz is meant for beginner and advanced students as well as professionals already working in the HR field.
Motivation
This tests some key elements of major motivation theories.
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.
Managing the Older Worker
This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce
Situational Leadership
This quiz will help you better understand Situational Leadership and its theories.