Purchase Solution

Draw an activity-on-arrow diagram for the project. b) Using the normal activity times (in weeks), carry out the forward and the backward pass calculations. Identify the critical path (A-B-D-F-H), the total project time and total normal project cost.

Not what you're looking for?

Ask Custom Question

Consider the project described:
See attached file for the project data.

a) Draw an activity-on-arrow diagram for the project.
b) Using the normal activity times (in weeks), carry out the forward and the backward pass calculations. Identify the critical path (A-B-D-F-H), the total project time and total normal project cost.
c) Determine which activities to crash and by how much to achieve a project completion time of 36 weeks at minimum cost. Provide a crash table.

Attachments
Purchase this Solution

Solution Summary

See attached document for diagram and solution.

Purchase this Solution


Free BrainMass Quizzes
Writing Business Plans

This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.

Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Understanding the Accounting Equation

These 10 questions help a new student of accounting to understand the basic premise of accounting and how it is applied to the business world.

IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)