Critical Path Method
Not what you're looking for?
Using the data in the table, complete the following
· Draw a network diagram
· Perform the forward and backward pass : determine the ES, EF, LS and LF dates
· Determine and identify the critical path
· What is the duration of the project ? Which activities have a float ?
· Develop a profile of the amounts to be spent per month based on your project schedule
· What is the total project budget at completion
Activity Predecessor Duration Total Cost
A - 5 $5,000
B - 10 10,000
C A, B 7 7,000
D C 12 12,000
E D 15 15,000
F D, E 12 12,000
G C, F 8 8,000
I E, G 9 9,000
J I 10 10,000
Purchase this Solution
Solution Summary
Draw a network diagram, perform the forward and backward pass to determine the ES, EF, LS and LF dates, determines and identifies the critical path, calculates the duration of the project, identifies the activities that have a float, develops a profile of the amounts to be spent per month based on the project schedule and calculates total project budget at completion.
Purchase this Solution
Free BrainMass Quizzes
IPOs
This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)
Production and cost theory
Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.
Lean your Process
This quiz will help you understand the basic concepts of Lean.
Introduction to Finance
This quiz test introductory finance topics.
Academic Reading and Writing: Critical Thinking
Importance of Critical Thinking