Activity Activity Time(weeks) Immediate Predecessor(s)
A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F

Calculate the completion time for the project. (Completion time = weeks)

Determine which activities are included on the critical path.

A, B, D, F, G
A, B, C, E, G

Purchase this Solution

Solution Summary

The solution determines the project completion time by critical path method.

Solution Preview

Please refer attached file for diagram.

Calculate the completion time for the project.

Please refer ...

Solution provided by:
Education
  • BEng (Hons) , Birla Institute of Technology and Science, India
  • MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
  • "Thank you"
  • "Really great step by step solution"
  • "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
  • "Thanks Again! This is totally a great service!"
  • "Thank you so much for your help!"
Purchase this Solution


Free BrainMass Quizzes
Basics of corporate finance

These questions will test you on your knowledge of finance.

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Transformational Leadership

This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking