Project Management : CPM/PERT Techniques
Not what you're looking for?
Use the following project information.
Activity Activity Time(weeks) Immediate Predecessor(s)
A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F
Calculate the completion time for the project. (Completion time = weeks)
Determine which activities are included on the critical path.
A, B, D, F, G
A, B, C, E, G
Purchase this Solution
Solution Summary
The solution determines the project completion time by critical path method.
Solution Preview
Please refer attached file for diagram.
Calculate the completion time for the project.
Please refer ...
Education
- BEng (Hons) , Birla Institute of Technology and Science, India
- MSc (Hons) , Birla Institute of Technology and Science, India
Recent Feedback
- "Thank you"
- "Really great step by step solution"
- "I had tried another service before Brain Mass and they pale in comparison. This was perfect."
- "Thanks Again! This is totally a great service!"
- "Thank you so much for your help!"
Purchase this Solution
Free BrainMass Quizzes
Basics of corporate finance
These questions will test you on your knowledge of finance.
Situational Leadership
This quiz will help you better understand Situational Leadership and its theories.
Transformational Leadership
This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.
Cost Concepts: Analyzing Costs in Managerial Accounting
This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.
Academic Reading and Writing: Critical Thinking
Importance of Critical Thinking