Critical Path Project Time
Activity Immediate Predecessor Time (WEEKS)
A -- 1
B A 4
C A 3
D B 2
E C,D 5
F D 2
G F 2
H E,G 3
a. Draw the network.
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
https://brainmass.com/business/project-management/critical-path-project-time-502248
Solution Preview
Please refer attached file for complete solution.
b. What is the critical path?
Critical path is indicated by dark arrows on the above ...
Solution Summary
The solution determines the project completion time by using Critical Path Method.