Purchase Solution

Constructing Networks, Scheduling and probability

Not what you're looking for?

Ask Custom Question

Please view the attached pdf and complete a network diagram and respond to the questions.

1. Scheduled completion of the project
2. Critical path of the project
3. EST, LST, EF and LF for activities
4. Float for activities
5. Scheduled completion time for project

Attachments
Purchase this Solution

Solution Summary

Answer four activity in box (AIB) problems on network construction, one comprehensive problem on network construction and one problem on scheduling and probability. This could be used as a good practice for project management.

Solution Preview

See the attached file. Thanks

Problem 1:
Network Diagram

Activity Analysis for Problem 1

Activity On Critical Activity Earliest Earliest Latest Latest Slack
Name Path Time Start Finish Start Finish (LS-ES)
1 A no 3 0 3 1 4 1
2 B Yes 4 0 4 0 4 0
3 C no 6 0 6 2 8 2
4 D Yes 2 4 6 4 6 0
5 E no 1 6 7 8 9 2
6 F Yes 3 6 9 6 9 0
7 G Yes 3 9 12 9 12 0
8 H no 7 6 13 15 22 9
9 I Yes 10 12 22 12 22 0

Project Completion Time = 22 Days
Number of Critical Path(s) = 1

(A) As seen from the network diagram the scheduled completion of the project is 22 days.
(B) The critical path is indicated on the network diagram with red color and shown in the able table with as "Yes" in Table under "On Critical Path" column. The critical path is
B - D - F - G - I
The length of critical path is 22 days.
(C) As seen in table, EST for activity D is 4 Days from start.
(D) As seen in table, LST for activity G is 9 Days from start.
(E) As seen in table, EF for ...

Purchase this Solution


Free BrainMass Quizzes
Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Accounting: Statement of Cash flows

This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.

Transformational Leadership

This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.

Business Processes

This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.

Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce