    Project network & critical path

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    See attached file.for full description.

    ---
    Note: If you can include a graph of the PERT or CPM, then please do.
    9. Tulsa Parks is planning to develop a new park and recreational area on a recently purchased 100-acre tract. Project development activities include clearing playground & picnic areas, constructing roads, constructing a shelter home, purchasing picnic equipment, & etc. The following network & activity times (in weeks) are being used in the planning, scheduling, & controlling this project.

    Activity A B C D E F G H I
    Activity Time 9 6 6 3 0 3 2 6 3
    a. What is the critical path for this network?
    b. Show activity schedule for this project.
    c. The commissioner would like to open the park to the public within 6 months from the time the work on the project is started. Does this opening date appear to be feasible? Explain
    ---

    © BrainMass Inc. brainmass.com October 9, 2019, 5:31 pm ad1c9bdddf
    https://brainmass.com/business/project-management/project-network-critical-path-60057

    Attachments

    Solution Summary

    This solution develops a critical path for a project for Tusla Parks.