Explore BrainMass
Share

Work Breakdown structure and Critical Path Management

Using the figure in the attachment, answer the following questions:

a. What is the critical path?
b. What is the expected activity duration?
c. How much slack is available in the noncritical path?
d. Upon changing to a late-finish schedule, what would be the new duration?
e. Reconfigure the network as a critical chain network. What is the new duration of the project?
f. How long is the project buffer?
g. How long is the feeder buffer?

© BrainMass Inc. brainmass.com August 14, 2018, 3:02 pm ad1c9bdddf

Attachments

Solution Preview

This is basically understanding the work breakdown structure.

a) critical path is the path that would lead to delays in the project. So, the path with the most amount of hrs would be the critical path.
A-B-E

b) The longest time....because A-B and C-D ...

Solution Summary

Undestanding how to determine the critical path, late finish, and critical chain network.

$2.19