Using the following table of tasks,
a. Build using MSP an mpp file including a work breakdown structure and a Gantt chart showing the project critical path.
b. What does the critical path become if Task C takes three time units?

Task Predecessor(s) Time units required
A None 1
B A 2
C A 1
D B and C 1

Attachments
Purchase this Solution

Solution Summary

Use Microsoft Project to create a Gantt chart and work breakdown structure. Answer questions regarding critical path.

Solution Preview

Please see the attached.

I have tried to provide sufficient information for you to complete your assignment. If you use this material in your work, please remember to cite BrainMass properly.

Remember that my job as an OTA is NOT to complete the work for you, but to provide you with ideas, definitions, research help, and instructions on how you should approach the assignment. ...

Purchase this Solution


Free BrainMass Quizzes
Lean your Process

This quiz will help you understand the basic concepts of Lean.

Operations Management

This quiz tests a student's knowledge about Operations Management

Introduction to Finance

This quiz test introductory finance topics.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.