Project management using diagrams and critical path
Not what you're looking for?
activity/duration days/precedes
a start/1/b,c
activity/duration days/ precedes
b/ 1/ / e
c/ 4 / / f
e/ 2/ / f
f/ 2/ / ----
1. Draw an AON diagram for the project use only circles and arrows.
2. Define the critical path, listing all critical activities in chronological order.
3. Outline if the project can be completed in ten days.
Purchase this Solution
Solution Summary
This is a step-by-step guide in solving PERT and CPM in Excel.
Solution Preview
The solution which includes AON diagram, critical path, and project ...
Purchase this Solution
Free BrainMass Quizzes
Economic Issues and Concepts
This quiz provides a review of the basic microeconomic concepts. Students can test their understanding of major economic issues.
Basics of Economics
Quiz will help you to review some basics of microeconomics and macroeconomics which are often not understood.
Pricing Strategies
Discussion about various pricing techniques of profit-seeking firms.
Elementary Microeconomics
This quiz reviews the basic concept of supply and demand analysis.
Economics, Basic Concepts, Demand-Supply-Equilibrium
The quiz tests the basic concepts of demand, supply, and equilibrium in a free market.