Project management using diagrams and critical path

Not what you're looking for?

Ask Custom Question

activity/duration days/precedes
a start/1/b,c
activity/duration days/ precedes
b/ 1/ / e
c/ 4 / / f
e/ 2/ / f
f/ 2/ / ----
1. Draw an AON diagram for the project use only circles and arrows.
2. Define the critical path, listing all critical activities in chronological order.
3. Outline if the project can be completed in ten days.

Purchase this Solution

Solution Summary

This is a step-by-step guide in solving PERT and CPM in Excel.

Solution Preview

The solution which includes AON diagram, critical path, and project ...

Purchase this Solution


Free BrainMass Quizzes
Economic Issues and Concepts

This quiz provides a review of the basic microeconomic concepts. Students can test their understanding of major economic issues.

Basics of Economics

Quiz will help you to review some basics of microeconomics and macroeconomics which are often not understood.

Pricing Strategies

Discussion about various pricing techniques of profit-seeking firms.

Elementary Microeconomics

This quiz reviews the basic concept of supply and demand analysis.

Economics, Basic Concepts, Demand-Supply-Equilibrium

The quiz tests the basic concepts of demand, supply, and equilibrium in a free market.