Explore BrainMass
Share

Explore BrainMass

    Project management using diagrams and critical path

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    activity/duration days/precedes
    a start/1/b,c
    activity/duration days/ precedes
    b/ 1/ / e
    c/ 4 / / f
    e/ 2/ / f
    f/ 2/ / ----
    1. Draw an AON diagram for the project use only circles and arrows.
    2. Define the critical path, listing all critical activities in chronological order.
    3. Outline if the project can be completed in ten days.

    © BrainMass Inc. brainmass.com October 10, 2019, 6:41 am ad1c9bdddf
    https://brainmass.com/economics/finance/project-management-diagrams-critical-path-553207

    Solution Preview

    The solution which includes AON diagram, critical path, and project ...

    Solution Summary

    This is a step-by-step guide in solving PERT and CPM in Excel.

    $2.19