    activity/duration days/precedes
    a start/1/b,c
    activity/duration days/ precedes
    b/ 1/ / e
    c/ 4 / / f
    e/ 2/ / f
    f/ 2/ / ----
    1. Draw an AON diagram for the project use only circles and arrows.
    2. Define the critical path, listing all critical activities in chronological order.
    3. Outline if the project can be completed in ten days.