Share
Explore BrainMass

Determining the critical path and project completion time

Activity Immediate Predecessor (Time Weeks)
A - 1
B A 4
C A 3
D B 2
E C ,D 5
F D 2
G F 2
H E, G 3

a) Draw the project network.
b) How many weeks will it take to complete the project?
c) Which activities have slack, and how much?
d) What is the revised completion time for the project if duration of activity E is 3 weeks?

Solution Preview

Please refer attached file for missing tables and diagrams.

b) How many weeks will it take to complete the project?
Project completion time=time taken by activities ...

Solution Summary

Solution provides the diagrams and detailed calculations to determining the critical path and expected project completion time.

$2.19