    ACC 231 Practice Problems Name
    Mr. McDermott

    1. Viking Sports is a manufacturer of sportswear. It produces all of its products in one department. The information for the current month is as follows:

    Beginning work in process 20,000 units
    Units started 40,000 units
    Units completed 50,000 units
    Ending work in process 8,000 units
    Spoilage 2,000 units

    Beginning work-in-process direct materials $12,000
    Beginning work-in-process conversion $ 4,000
    Direct materials added during month $60,000
    Direct manufacturing labor during month $20,000

    Beginning work in process was half complete as to conversion. Direct materials are added at the beginning of the process. Factory overhead is applied at a rate equal to 50% of direct manufacturing labor. Ending work in process was 60% complete. All spoilage is normal and is detected at end of the process.

    Required:

    Prepare a production cost worksheet if spoilage is recognized and the weighted-average method is used. (Show all work)

    2. For supply item ABC, Andrews Company has been ordering 125 units based on the recommendation of the salesperson who calls on the company monthly. A new purchasing agent has been hired by the company who wants to start using the economic-order-quantity method and its supporting decision elements. She has gathered the following information:
    Annual demand in units 250
    Days used per year 250
    Lead time, in days 10
    Ordering costs $100
    Annual unit carrying costs $20

    Required:

    Determine the EOQ, average inventory, orders per year, average daily demand, reorder point, annual ordering costs, and annual carrying costs. (Show all work)
    3. The Jarvis Corporation produces bucket loader assemblies for the tractor industry. The product has a long term life expectancy. Jarvis has a traditional manufacturing and inventory system. Jarvis is considering the installation of a just-in-time inventory system to improve its cost structure. In doing a full study using its manufacturing engineering team as well as consulting with industry JIT experts and the main vendors and suppliers of the components Jarvis uses to manufacture the bucket loader assemblies, the following incremental cost-benefit relevant information is available for analysis:

    The Jarvis cost of investment capital hurdle rate is 15%.
    One time cost to rearrange the shop floor to create the manufacturing cell workstations is $275,000.
    One time cost to retrain the existing workforce for the JIT required skills is $60,000.
    Anticipated defect reduction is 40%. Currently there is a cost of quality defect assessment listed as $150,000 per year.
    The setup time for each of the existing functions will be reduced by 67%. Currently the forecast for setup costs are $225,000 per year.
    Jarvis will expect to save $200,000 per year in carrying costs as a result of having a lower inventory.

    The suppliers will require a 15% premium over the current level of prices in order to position themselves to supply the material on a smaller and more frequent schedule. Currently the materials purchases are $1,500,000 per year.

    Required:

    Determine whether it is in the best interest of Jarvis Corporation to install a JIT system. (Show all work)

    4. Vision Enterprises manufactures converter boxes for high definition TVs. All processing is initiated when an order is received. For March there were no beginning inventories. Conversion Costs and Direct Materials are the only manufacturing cost accounts. Direct Materials are purchased under a just-in-time system. Backflush costing is used with a finished goods trigger point. Additional information is as follows:

    Actual conversion costs $435,000
    Standard materials costs per unit 115
    Standard conversion cost per unit 85
    Units produced 7,900
    Units sold 7,600

    Required:

    Record all journal entries for the monthly activities related to the above transactions if backflush costing is used. (Show all work)

    © BrainMass Inc. brainmass.com October 10, 2019, 2:51 am ad1c9bdddf
    https://brainmass.com/business/balanced-scorecard/cost-accounting-balanced-scorecards-396794

    Attachments

    Solution Preview

    Hello

    Please find the solutions attached.

    ACC 231 Practice Problems Name
    Mr. McDermott

    1. Viking Sports is a manufacturer of sportswear. It produces all of its products in one department. The information for the current month is as follows:

    Beginning work in process 20,000 units
    Units started 40,000 units
    Units completed 50,000 units
    Ending work in process 8,000 units
    Spoilage 2,000 units

    Beginning work-in-process direct materials $12,000
    Beginning work-in-process conversion $ 4,000
    Direct materials added during month $60,000
    Direct manufacturing labor during month $20,000

    Beginning work in process was half complete as to conversion. Direct materials are added at the beginning of the process. Factory overhead is applied at a rate equal to 50% of direct manufacturing labor. Ending work in process was 60% complete. All spoilage is normal and is detected at end of the process.

    Required:

    Prepare a production cost worksheet if spoilage is recognized and the weighted-average method is used. (Show all work)

    PRODUCTION COST WORKSHEET

    Flow of Production Physical units Direct materials Conversion
    Work in process, beginning 20,000
    Started during period 40,000
    To account for 60,000

    Good units completed 50,000 50,000 50,000
    Normal spoilage 2,000 2,000 2,000
    Work in process, ending 8,000 8,000 4,800
    Accounted for 60,000 60,000 56,800

    Costs Totals Direct Materials Conversion
    Work in process, beginning $ 16,000 $12,000 $ 4,000
    Costs added during ...

    Solution Summary

    Costing accounting balanced scorecards are examined.

    $2.19