Explore BrainMass
Share

Web Sites Analysis

This content was STOLEN from BrainMass.com - View the original, and get the already-completed solution here!

Access the following web sites and report on the type(s) of information/data that are available: I also want your opinions regarding the web sites.

1. www.epa.gov
2. www.ftc.gov
3. www.pirg.org

Thank you.

© BrainMass Inc. brainmass.com October 24, 2018, 9:09 pm ad1c9bdddf
https://brainmass.com/sociology/criminology-law-deviance-and-punishment/web-sites-analysis-118411

Solution Preview

Please see response attached, which is also presented below.

RESPONSE:

1. The U.S. Environmental Protection Agency (EPA) has various types of information, including the following (each are hyperlinked in the attached response):

· EPA Newsroom
· Browse EPA Topics
· Laws, Regulations & Dockets
· Where You Live
· Frequent Questions
· Information Sources
· Educational Resources
· About EPA
· Programs
· Partnerships
· Business Opportunities
· Careers
· EPA En Español

E.g. Mission: "The mission of the Environmental Protection Agency is to protect human health and the environment. Since 1970, EPA has been working for a cleaner, healthier environment for the American people. View ...

Solution Summary

This solution accesses the following web sites and reports on the type(s) of information/data that are available.

$2.19
See Also This Related BrainMass Solution

Scheduling and Project Management (Operations Management)

How would you crash a project (which activities would you crash) to keep the project on schedule and achieve the original duration, if Activity B actually takes 5 weeks instead of the planned 3 weeks? (Explain your logic)?

Activity Description Predecessor Normal Time (weeks) Normal Cost Crash Time (weeks) Crash Cost
A Finalize site and building contracts --- 7 $7,500 4 $11,500
B Select local printer A 3 $500 2 $800
C Hire production manager A 3 $1,200 2 $1,700
D Design promotional Web site B 5 $6,000 3 $9,000
E Set TV deal D 6 $4,000 4 $6,500
F Hire director E 4 $1,200 3 $1,700
G Plan for TV camera placement F 2 $500 2 $500
H Target headline entertainers B 4 $2,000 3 $3,500
I Target support entertainers H 4 $2,000 3 $3,500
J Travel accommodations for talent I 10 $9,000 7 $16,000
K Set venue capacity C 2 $300 1 $400
L Ticketmaster contract D 3 $1,400 2 $1,900
M On-site ticketing L 8 $7,000 6 $11,000
N Sound and staging C 6 $9,000 5 $12,000
O Passes and stage credentials G 7 $4,000 5 $5,800
P Travel accommodations for staff B 20 $15,000 15 $23,000
Q Hire sponsor coordinator B 4 $600 3 $800
R Finalize sponsors Q 4 $1,000 3 $1,400
S Define/place signage for sponsors R 3 $3,000 2 $4,200
T Hire operations manager A 4 $1,200 2 $1,800
U Develop site plan T 6 $6,000 5 $8,500
V Hire security director T 7 $1,500 5 $3,000
W Set police/fire security plan V 4 $1,000 3 $1,600
X Power, plumbing, AC, toilet services U 8 $4,000 6 $7,000
Y Secure merchandise deals B 6 $6,000 3 $7,500
Z Online merchandise sales Y 6 $5,000 4 $7,500