    Scheduling Problem

    Not what you're looking for? Search our solutions OR ask your own Custom question.

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. Can they complete the project in the 38 class days remaining until the end of the semester?

    Activity Time Immediate Predecessors

    A. Find client 4 --
    B. Write prospectus 2 A
    C. Obtain approval from client and professor 3 B
    D. Complete programming 12 C
    E. Do industry background research 10 --
    F. Write final paper 6 D, E
    G. Write oral report 5 D, E

    © BrainMass Inc. brainmass.com December 15, 2022, 8:02 pm ad1c9bdddf
    https://brainmass.com/math/linear-programming/scheduling-problem-268515

    Solution Summary

    This solution is comprised of detailed explanation and step-by-step calculation of the given problem and provides students with a clear perspective of the underlying concepts.

    $2.49

    ADVERTISEMENT