Explore BrainMass
Share

Discrete Math: Quantitative Method

This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

You are working on a project that has 12 activities and wand to perform aCPM analysis on a project. You determine the critical path consists of only five actives. You then compute the variances for the five critical path activities and these variances 3, 4, 2, 1, and 6 days. If the desired completion date for the project is 50 days and the expected completion date for the project is 40 days, what is the probability that the project will be completed by the desired completion date?

© BrainMass Inc. brainmass.com March 21, 2019, 11:53 pm ad1c9bdddf
https://brainmass.com/math/finite-element-method/discrete-math-quantitative-method-477991

Solution Summary

This solution provides a detailed, step-by-step explanation of the given problem.

$2.19