Company X has been told to install some new equipment. The company has 16 weeks to install the equipment. Using the following information:
IMMEDIATE ACTIVITY TIMES
ACTIVITY PREDECESSORS a m b
A --- 1 2 3
B --- 2 3 4
C A 1 2 3
D B 2 4 6
E C 1 4 7
F C 1 2 9
G D, E 3 4 11
H F, G 1 2 3
1.) What is the Critical Path?
2.) What is the expected completion time?
3.) Which activities have slack time and what are their respected slack times?
4.) What is the probability that the project can be completed in 16 weeks? (Show Work)
Purchase this Solution
Solution Summary
The problem set deals with estimating project duration, probability of completion etc under Program evaluation and review technique methodology.
Education
- B. Sc., University of Nigeria
- M. Sc., London South Bank University
Recent Feedback
- "Thank you."
- "thank you Chidi Ngene.. if you have any APA references would be great"
- "Thank you so much for your help, your explanations were easy to understand and apply!"
- "are you able to highlight the equations used either on the xlsx or a word doc as to how each graph was formed- overall looks fine i just need help understanding this myself"
- "Chidi Ngene, M. Sc. Was extremely helpful as without the help and guidance I would have failed, but with the help I passed. I still have a lot to learn and in need of the guidance to understand and learn more on the subject. I would recommend Chidi Ngene and BrainMass to anyone that are in need of help. Thank you!!"
Purchase this Solution
Free BrainMass Quizzes
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.
Organizational Behavior (OB)
The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.
Marketing Research and Forecasting
The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.
Income Streams
In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.
Learning Lean
This quiz will help you understand the basic concepts of Lean.