    Critical path and time to completion of project

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Calculate critical path and time to completion of project based upon data supplied in excel sheet.

    ACTIVITY SCHEDULED TIME PRECEDENCE ACTIVITY
    1 Proposal and review 1 mo --
    2 Establish master schedule 2 wk 1
    3 Architect selection process 1.25 mo 1
    4 Survey campus and needs 1 mo 1
    5 Conceptual architect plans 1.5 mo 3
    6 cost estimating 2 mo 2,4,5
    7 deliver plans to board for consideration 1 mo 6
    8 surveys/regulatory review 1.5 mo 6
    9 construction manager selection 2.25 mo 6
    10 state review of need 3.5 mo 7,8
    11 design drawings 4 mo 10
    12 construction documents 5 mo 9,11
    13 site preparation/demolish existing building 2.25 mo 11
    14 construction start/building pad 2 mo 12,13
    15 relocate utilities 1.5 mo 12
    16 deep foundations 2 mo 14
    17 building structure in place 9 mo 16
    18 exterior skin/roofing 4 mo 17
    19 interior buildout 12 mo 17
    20 building inspections 1.25 mo 15,19
    21 occupancy 1 mo 20

    © BrainMass Inc. brainmass.com June 3, 2020, 9:55 pm ad1c9bdddf
    https://brainmass.com/business/project-management/critical-path-and-time-to-completion-of-project-205428

    Attachments

    Solution Summary

    Identifies critical path and calculates time to completion of project