Critical path and time to completion of project

Calculate critical path and time to completion of project based upon data supplied in excel sheet.

ACTIVITY SCHEDULED TIME PRECEDENCE ACTIVITY
1 Proposal and review 1 mo --
2 Establish master schedule 2 wk 1
3 Architect selection process 1.25 mo 1
4 Survey campus and needs 1 mo 1
5 Conceptual architect plans 1.5 mo 3
6 cost estimating 2 mo 2,4,5
7 deliver plans to board for consideration 1 mo 6
8 surveys/regulatory review 1.5 mo 6
9 construction manager selection 2.25 mo 6
10 state review of need 3.5 mo 7,8
11 design drawings 4 mo 10
12 construction documents 5 mo 9,11
13 site preparation/demolish existing building 2.25 mo 11
14 construction start/building pad 2 mo 12,13
15 relocate utilities 1.5 mo 12
16 deep foundations 2 mo 14
17 building structure in place 9 mo 16
18 exterior skin/roofing 4 mo 17
19 interior buildout 12 mo 17
20 building inspections 1.25 mo 15,19
21 occupancy 1 mo 20

Attachments

Solution Summary

Identifies critical path and calculates time to completion of project