    PERT network

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Given the following table:
    1. Draw the network diagram
    2. Determine the critical path
    3. Calculate the expected duration and variance for each acitivity
    4. Calculate the expected duration and variance of the critical path
    5. Find the probability of completing the project in:
    a. Less than 22 weeks
    b. More than 25 weeks
    c. Between 23 and 28 weeks

    Time Estimates (weeks)
    Activity Immediate Predecessors Optimistic Most Likely Pessimistic
    A - 5 11 14
    B - 3 3 9
    C - 6 10 14
    D A,B 3 5 7
    E B 4 6 11
    F C 6 8 13
    G D,E 2 4 6
    H F,G 3 3 9

    Please see the attached question.

    © BrainMass Inc. brainmass.com June 3, 2020, 9:07 pm ad1c9bdddf
    https://brainmass.com/business/business-math/pert-network-problem-166737

    Attachments

    Solution Preview

    Please see attached file.

    Project Management (25%)

    Given the following table:
    1. Draw the network diagram
    2. Determine the critical path
    3. Calculate the expected duration and variance for each acitivity
    4. Calculate the expected duration and variance of the critical path
    5. Find the probability of completing the project in:
    a. Less than 22 weeks
    b. More than 25 weeks
    c. Between 23 and 28 weeks

    Time Estimates (weeks)
    Activity Immediate Predecessors Optimistic Most Likely Pessimistic
    A - 5 11 14
    B - 3 3 9
    C - 6 10 14
    D A,B 3 5 7
    E B 4 6 11
    F C 6 8 13
    G D,E 2 4 6
    H F,G 3 3 9

    1. Draw the network diagram

    D G H Finish

    A
    E

    Start B
    F

    C

    2. Determine the critical path

    The expected times are calculated in part c below
    Critical path consists of those activities whose slack is zero
    Earliest Start Time
    Latest Start ...

    Solution Summary

    Draws the network diagram, determine the critical path and finds the probability of completing the project before a specified period.