    1. Draw the PERT network, identify the earliest and latest start time for each activity and the amount of slack for non-critical activities
    Completion Immediate Earliest Latest Amount
    Activity Time Predecessor Start Start of Slack

    A 12 ---

    B 6 ---

    C 4 B

    D 5 B

    E 4 A

    F 2 C,D

    G 3 E,F

    H 2 E

    I 6 D

    © BrainMass Inc. brainmass.com March 4, 2021, 9:40 pm ad1c9bdddf
    https://brainmass.com/statistics/descriptive-statistics/pert-network-earliest-latest-start-time-262598

    Attachments

    Solution Preview

    1. Draw the PERT network, identify the earliest and latest start time for each activity and the amount of slack for non-critical activities
    Completion Immediate Earliest Latest Amount
    Activity Time Predecessor Start Start ...

    Solution Summary

    Step by step solutions to all questions are provided. Ths solution includes a PERT network.