PERT Problem

Activity Days * Immediate Predecessor
a m b
A 8 10 12 -
B 6 7 9 -
C 3 3 4 -
D 10 20 30 A
E 6 7 8 C
F 9 10 11 B,D.E
G 6 7 10 B,D,E
H 14 15 16 F
I 10 11 13 F
J 6 7 8 G, H
K 4 7 8 I, J
L 1 2 4 G, H

* a=Optimistic time
m=Most probable or likely time
b=Pessimistic time

Solve for:

A) Construct a network for this problem
B) Determine expected time and variance for each activity
C) Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest finish time(LF), and slack time for each activity
D)Determine critical path and project completion time
E)Determine the probability that the project will be finished in 70 days or less
F) Determine the probability that the project will be finished in 80 days or less
G)Determine the probability that the project will be finished in 90 days or less

Please use Excel or QM for windows and explain as much as possible.

Solution Summary

This posting contains solution to following PERT Problem including:PERT, Network construction, ES, LS, EF, LF, Probability of finishing in given time, CPM