    A PERT problem: calculating variance of critical path

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Consider the tasks, durations, and predecessor relationships in the following network.

    (see chart in attached file)

    a. Draw the network:
    b. Calculate Te for all tasks (fill in the table):
    c. Calculate variance for all tasks (fill in the table):
    d. Determine all paths, their estimated durations, and their variances:
    e. Identify the critical path:
    f. What is the likelihood (probability) of completing the project in 42 weeks?

    © BrainMass Inc. brainmass.com June 3, 2020, 6:58 pm ad1c9bdddf
    https://brainmass.com/business/business-math/pert-problem-calculating-variance-critical-path-81488

    Attachments

    Solution Summary

    This posting contains a typical PERT problem with drawing the Network diagram, calculating Te, determining Critical path, and Variance of critival path and calculating Probability of completing the project in given time.