Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest finish time(LF), and slack time for each activity

Solve for:
A) Construct a network for this problem
B) Determine expected time and variance for each activity
C) Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest finish time(LF), and slack time for each activity
D)Determine critical path and project completion time

Purchase this Solution

Solution Summary

Solution in attached excel document.

Purchase this Solution


Free BrainMass Quizzes
Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.

Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.