Purchase Solution

CPM Question - Activity Times

Not what you're looking for?

Ask Custom Question

The following represents a project with known activity times. All times are in weeks.
Activity Predecessor Immediate Time
A - 4
B - 3
C A 2
D B 7
E C, D 4
F B 5
1. Using the data in the table above, what is the minimum possible time required for completing the project?
a.) 8
b.) 14
c.) 25
d.) 10
e.) none of the above

2. Using the data in the table above, what is the latest possible time that C may be started without delaying completion of the project?
a.) 0
b.) 4
c.) 8
d.) 10
e.) none of the above

3. According to the table above, compute the slack time for activity D.
a.) 0
b.) 5
c.) 3
d.) 6
e.) none of the above

Purchase this Solution

Solution Preview

1. Using the data in the table above, what is the minimum possible time required for completing the project?
a.) 8
Hint:
Start ? B ? F ? Finish
That is, 3 + 5 = 8 weeks

2. Using the data in ...

Purchase this Solution


Free BrainMass Quizzes
Geometry - Real Life Application Problems

Understanding of how geometry applies to in real-world contexts

Know Your Linear Equations

Each question is a choice-summary multiple choice question that will present you with a linear equation and then make 4 statements about that equation. You must determine which of the 4 statements are true (if any) in regards to the equation.

Solving quadratic inequalities

This quiz test you on how well you are familiar with solving quadratic inequalities.

Graphs and Functions

This quiz helps you easily identify a function and test your understanding of ranges, domains , function inverses and transformations.

Probability Quiz

Some questions on probability