Specifying the critical path and calculate the slack
Not what you're looking for?
Activity Immediate Predecessor(s) Activity Time (days)
A - 4
B - 3
C - 5
D A, B 3
E B 6
F D, C 4
G E, C 8
H F, G 12
a. Draw the network diagram for this project.
b. Specify the critical path.
c. Calculate the slack for activities A and D.
d. What happens to the slack for activity D if A takes five weeks?
Purchase this Solution
Solution Summary
This solution assists in drawing a network diagram, specifying the critical path and calculates the slack.
Education
- B. Sc., University of Nigeria
- M. Sc., London South Bank University
Recent Feedback
- "Thank you."
- "thank you Chidi Ngene.. if you have any APA references would be great"
- "Thank you so much for your help, your explanations were easy to understand and apply!"
- "are you able to highlight the equations used either on the xlsx or a word doc as to how each graph was formed- overall looks fine i just need help understanding this myself"
- "Chidi Ngene, M. Sc. Was extremely helpful as without the help and guidance I would have failed, but with the help I passed. I still have a lot to learn and in need of the guidance to understand and learn more on the subject. I would recommend Chidi Ngene and BrainMass to anyone that are in need of help. Thank you!!"
Purchase this Solution
Free BrainMass Quizzes
Six Sigma for Process Improvement
A high level understanding of Six Sigma and what it is all about. This just gives you a glimpse of Six Sigma which entails more in-depth knowledge of processes and techniques.
Transformational Leadership
This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.
Writing Business Plans
This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Business Processes
This quiz is intended to help business students better understand business processes, including those related to manufacturing and marketing. The questions focus on terms used to describe business processes and marketing activities.