Network diagram and identify all the path

Not what you're looking for?

Ask Custom Question

Given the information in the following table

Activity Duration Predecessor
a 4 None
b 6 a
c 4 a
d 2 c
e 4 b
f 5 b, d
g 3 c
h 4 f,g
i 2 e, h

a. Construct the network diagram
b. Identify each activity's EST, EFT, LST adn LFT
c. Identify all paths. Which path is the critical path?
d. Calculate the slack each activity?
e. How long will it take to complete the project?

Purchase this Solution

Solution Summary

This post shows how to construct the network diagram, identify all the path and how to calculate slack, EST, EFT, LST and LFT

Solution Preview

See the attached file. Thanks

Given the information in the following table

Activity Duration Predecessor
a 4 None
b 6 a
c 4 a
d 2 c
e 4 ...

Purchase this Solution


Free BrainMass Quizzes
Accounting: Statement of Cash flows

This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.

Production and cost theory

Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Writing Business Plans

This quiz will test your understanding of how to write good business plans, the usual components of a good plan, purposes, terms, and writing style tips.