    Given the information in the following table

    Activity Duration Predecessor
    a 4 None
    b 6 a
    c 4 a
    d 2 c
    e 4 b
    f 5 b, d
    g 3 c
    h 4 f,g
    i 2 e, h

    a. Construct the network diagram
    b. Identify each activity's EST, EFT, LST adn LFT
    c. Identify all paths. Which path is the critical path?
    d. Calculate the slack each activity?
    e. How long will it take to complete the project?

    © BrainMass Inc. brainmass.com March 4, 2021, 10:47 pm ad1c9bdddf
    https://brainmass.com/business/project-management/network-diagram-and-identify-all-the-path-362385

    Solution Preview

    See the attached file. Thanks

    Given the information in the following table

    Activity Duration Predecessor
    a 4 None
    b 6 a
    c 4 a
    d 2 c
    e 4 ...

    Solution Summary

    This post shows how to construct the network diagram, identify all the path and how to calculate slack, EST, EFT, LST and LFT