Explore BrainMass
Share

Construct a network diagram, identify the critical path

This content was STOLEN from BrainMass.com - View the original, and get the solution, here!

The following data were obtained from a project to build a pressure vessel:

Activity Duration Predecessors
A 4 weeks ---
B 4 weeks ---
C 3 weeks B
D 2 weeks A, C
E 3 weeks B
F 5 weeks D, E, G
G 2 weeks B
H 6 weeks F
I 3 weeks G
J 1 week I

Construct a network for the project. Then review and answer (A) and (B).

(A.) Calculate the scheduled completion time and identify the critical path.

(B.) What is the slack time (float) for activities A, D, E, and G?

© BrainMass Inc. brainmass.com September 21, 2018, 11:17 pm ad1c9bdddf - https://brainmass.com/business/project-management/construct-a-network-diagram-identify-the-critical-path-343779

Solution Preview

Please see the word document which does a better job of formatting and showing the diagram I prepared for your study.

The following data were obtained from a project to build a pressure vessel:

Activity Duration Predecessors
A 4 weeks ---
B 4 weeks ---
C 3 weeks B
D 2 weeks A, C
E 3 weeks B
F 5 weeks D, E, G
G 2 weeks B
H 6 weeks F
I 3 weeks G
J 1 week I

Construct a network for the project. Then review and answer the multi-part question.

For ...

Solution Summary

This post shows how to construct a network for the project. It shows how to calculate the schedule completion time and identify the critical path.

$2.19