Share
Explore BrainMass

AIB Problems

Can you provide me with a little help with a few AIB problems so I can gain an understanding of the concept?

Solution Preview

Title: AIB Problems

Short Summary: Network Diagrams: AIB Problems

Long Summary: Can you provide me with a little help with a few AIB problems so I can gain an understanding of the concept?

Abstract: Having trouble with AIB problems? This excerpt will provide you with a few simple examples that will help walk you through the solutions. It also provides you with the definitions of slack, float, free slack, and the critical path.

Keywords: aib, problems, network, diagrams, concept, solutions, understanding, data, critical, path

Solutions:

Problem 1

The following data were obtained from a project to create a new portable electronic.

Activity Duration Predecessors
A 5 Days ---
B 6 Days ---
C 8 Days ---
D 4 Days A, B
E 3 Days C
F 5 Days D
G 5 Days E, F
H 9 Days D
I 12 Days G

Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions:

a) What is the Scheduled Completion of the Project?

32

b) What is the Critical Path of the Project?

BDFGI

c) What is the ES for Activity D?

6

d) What is the LS for Activity G?

15

e) What is the EF for Activity B?

6

f) What is the LF for Activity H?

15
g) What is the float for Activity I?

32-20 = 12