Explore BrainMass

Explore BrainMass

    AIB Problems

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Can you provide me with a little help with a few AIB problems so I can gain an understanding of the concept?

    © BrainMass Inc. brainmass.com June 4, 2020, 2:58 am ad1c9bdddf
    https://brainmass.com/business/business-management/aib-problems-491639

    Solution Preview

    Title: AIB Problems

    Short Summary: Network Diagrams: AIB Problems

    Long Summary: Can you provide me with a little help with a few AIB problems so I can gain an understanding of the concept?

    Abstract: Having trouble with AIB problems? This excerpt will provide you with a few simple examples that will help walk you through the solutions. It also provides you with the definitions of slack, float, free slack, and the critical path.

    Keywords: aib, problems, network, diagrams, concept, solutions, understanding, data, critical, path

    Solutions:

    Problem 1

    The following data were obtained from a project to create a new portable electronic.

    Activity Duration Predecessors
    A 5 Days ---
    B 6 Days ---
    C 8 Days ---
    D 4 Days A, B
    E 3 Days C
    F 5 Days D
    G 5 Days E, F
    H 9 Days D
    I 12 Days G

    Step 1: Construct a network diagram for the project.
    Step 2: Answer the following questions:

    a) What is the Scheduled Completion of the Project?

    32

    b) What is the Critical Path of the Project?

    BDFGI

    c) What is the ES for Activity D?

    6

    d) What is the LS for Activity G?

    15

    e) What is the EF for Activity B?

    6

    f) What is the LF for Activity H?

    15
    g) What is the float for Activity I?

    32-20 = 12

    Problem 2

    The following data were obtained from a project to build a ...