    Creating network diagram, compute critical path, expected completion time

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Need all work shown, please see file for details.

    1. The following information has been gathered for a project
    a. Draw a network diagram
    b. Calculate the slack for each activity and determine the critical path. How long will the project take.

    Activity Activity Time (Weeks) Immediate Predecessor
    A 4 -
    B 7 A
    C 9 B
    D 3 B
    E 14 D
    F 10 C, D
    G 11 F, E

    © BrainMass Inc. brainmass.com October 2, 2020, 5:16 am ad1c9bdddf
    https://brainmass.com/business/project-management/578790

    Attachments

    Solution Preview

    1. The following information has been gathered for a project
    a. Draw a network diagram
    b. Calculate the slack for each activity and determine the critical path. How long will the project take.

    Activity Activity Time (Weeks) Immediate Predecessor
    A 4 -
    B 7 A
    C 9 B
    D 3 B
    E 14 D
    F 10 C, D
    G 11 F, E

    In creating a network diagram, computing slack activity, and determining the critical ...

    Solution Summary

    1. The following information has been gathered for a project
    a. Draw a network diagram
    b. Calculate the slack for each activity and determine the critical path. How long will the project take.
    Activity Activity Time (Weeks) Immediate Predecessor
    A 4 -
    B 7 A
    C 9 B
    D 3 B
    E 14 D
    F 10 C, D
    G 11 F, E