Creating network diagram, compute critical path, expected completion time
Not what you're looking for?
Need all work shown, please see file for details.
1. The following information has been gathered for a project
a. Draw a network diagram
b. Calculate the slack for each activity and determine the critical path. How long will the project take.
Activity Activity Time (Weeks) Immediate Predecessor
A 4 -
B 7 A
C 9 B
D 3 B
E 14 D
F 10 C, D
G 11 F, E
Purchase this Solution
Solution Summary
1. The following information has been gathered for a project
a. Draw a network diagram
b. Calculate the slack for each activity and determine the critical path. How long will the project take.
Activity Activity Time (Weeks) Immediate Predecessor
A 4 -
B 7 A
C 9 B
D 3 B
E 14 D
F 10 C, D
G 11 F, E
Solution Preview
1. The following information has been gathered for a project
a. Draw a network diagram
b. Calculate the slack for each activity and determine the critical path. How long will the project take.
Activity Activity Time (Weeks) Immediate Predecessor
A 4 -
B 7 A
C 9 B
D 3 B
E 14 D
F 10 C, D
G 11 F, E
In creating a network diagram, computing slack activity, and determining the critical ...
Purchase this Solution
Free BrainMass Quizzes
Operations Management
This quiz tests a student's knowledge about Operations Management
Marketing Research and Forecasting
The following quiz will assess your ability to identify steps in the marketing research process. Understanding this information will provide fundamental knowledge related to marketing research.
Marketing Management Philosophies Quiz
A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.
Academic Reading and Writing: Critical Thinking
Importance of Critical Thinking
Learning Lean
This quiz will help you understand the basic concepts of Lean.