    AON Project Network

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?

    ID.....Description..........Predecessor.......Time (days)
    A......Survey site..............None......................2
    B......Install drainage..........A.........................5
    C......Install power lines......A.........................3
    D......Excavate site.......... B, C...................... 4
    E......Pour foundation........D......................... 3

    © BrainMass Inc. brainmass.com June 4, 2020, 3:45 am ad1c9bdddf
    https://brainmass.com/business/business-management/aon-project-network-532575

    Solution Summary

    Solution develops AON diagram in the given case. It clearly indicates the forward and backward pass and determines the expected project completion time.