Shirley Hopkins is developing a program in leadership
training for middle-level managers. Shirley has listed a number of
activities that must be completed before a training program of this
nature could be conducted. The activities, immediate predecessors,
and times appear in the accompanying table:
Activity Immediate Predecessors Time (days)
A ----- 2
B ----- 5
C ----- 1
D B 10
E A,D 3
F C 6
G E,F 8
a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?

Solution Preview

NOTE: PLEASE SEE THE ATTACHED FILE FOR A DETAILED COMPUTATION.

Posting Requirement:
a) Develop an ...

Solution Summary

The solutions discusses in detail how to design, compute, and summarize an Activity on Node (AON) Problem. It discusses in detail the critical path and the project completion time. The detailed instruction is found in the attached file.