Activity on Node (AON) Network
Not what you're looking for?
Shirley Hopkins is developing a program in leadership
training for middle-level managers. Shirley has listed a number of
activities that must be completed before a training program of this
nature could be conducted. The activities, immediate predecessors,
and times appear in the accompanying table:
Activity Immediate Predecessors Time (days)
A ----- 2
B ----- 5
C ----- 1
D B 10
E A,D 3
F C 6
G E,F 8
a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?
Purchase this Solution
Solution Summary
The solutions discusses in detail how to design, compute, and summarize an Activity on Node (AON) Problem. It discusses in detail the critical path and the project completion time. The detailed instruction is found in the attached file.
Solution Preview
NOTE: PLEASE SEE THE ATTACHED FILE FOR A DETAILED COMPUTATION.
Posting Requirement:
a) Develop an ...
Purchase this Solution
Free BrainMass Quizzes
Organizational Behavior (OB)
The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.
Introduction to Finance
This quiz test introductory finance topics.
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Cost Concepts: Analyzing Costs in Managerial Accounting
This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.