    Activity on Node (AON) Network

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Shirley Hopkins is developing a program in leadership
    training for middle-level managers. Shirley has listed a number of
    activities that must be completed before a training program of this
    nature could be conducted. The activities, immediate predecessors,
    and times appear in the accompanying table:
    Activity Immediate Predecessors Time (days)
    A ----- 2
    B ----- 5
    C ----- 1
    D B 10
    E A,D 3
    F C 6
    G E,F 8
    a) Develop an AON network for this problem.
    b) What is the critical path?
    c) What is the total project completion time?

    © BrainMass Inc. brainmass.com June 4, 2020, 2:25 am ad1c9bdddf
    https://brainmass.com/business/business-management/activity-on-node-aon-network-456663

    Solution Preview

    NOTE: PLEASE SEE THE ATTACHED FILE FOR A DETAILED COMPUTATION.

    Posting Requirement:
    a) Develop an ...

    Solution Summary

    The solutions discusses in detail how to design, compute, and summarize an Activity on Node (AON) Problem. It discusses in detail the critical path and the project completion time. The detailed instruction is found in the attached file.