    From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?

    ID Description Predecessor Time
    A Identify Topic None 1
    B Research Topic A 10
    C Draft Paper B 4
    D Edit Paper C 4
    E Create Graphics C 2
    F References C 1
    G Final Draft D, E, F 3

    © BrainMass Inc. brainmass.com June 4, 2020, 3:24 am ad1c9bdddf
    https://brainmass.com/business/project-management/developing-aon-project-network-513228

    Solution Summary

    An Activity on Nodes project network has been developed. Using forward and backward pass activity slack is computed and the critical path identified.