    Activity on Node (AON) Network for Dave Carhart's Company

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Draw the activity-on-node (AON) project network
    associated with the following activities for Dave Carhart's consulting
    company project. How long should it take Dave and his team to
    complete this project? What are the critical path activities?

    Activity Immediate Predecessor(s) Time (days)
    A ----- 3
    B A 4
    C A 6
    D B 6
    E B 4
    F C 4
    G D 6
    H E,F 8