    Network Diagram (AON)

    This content was COPIED from BrainMass.com - View the original, and get the already-completed solution here!

    Please see attached table.

    1. Draw the network diagram (AON) showing the early start, late start, early finish and late finish times.
    2. Determine the paths and show the critical path.
    3. What is the slack time of each activity?

    © BrainMass Inc. brainmass.com June 4, 2020, 3:14 am ad1c9bdddf
    https://brainmass.com/business/business-management/network-diagram-aon-504923

    Attachments

    Solution Preview

    Please find the full solutions attached.

    Determine the paths and show the critical path.  

    Path Duration Critical?
    1-2-5-8-9-11 23 ...

    Solution Summary

    The solution includes the network diagram (AON) and provides a detailed solution determining the paths, showing the critical paths, and slack time (see attachment).