    Consider the following data for a project:

    Activity Activity Time (Days) Immediate Predecessor
    A 2 —
    B 4 A
    C 5 A
    D 2 B
    E 1 B
    F 8 B, C
    G 3 D, E
    H 5 F
    I 4 F
    J 7 G, H, I

    a. Draw the network diagram.
    b. Calculate the critical path for this project.
    c. How much slack is in activities G, H, and I?