Consider the following data for a project:

Activity Activity Time (Days) Immediate Predecessor
A 2 —
B 4 A
C 5 A
D 2 B
E 1 B
F 8 B, C
G 3 D, E
H 5 F
I 4 F
J 7 G, H, I

a. Draw the network diagram.
b. Calculate the critical path for this project.
c. How much slack is in activities G, H, and I?