Purchase Solution

Project Management: RAM & RACI Chart

Not what you're looking for?

Ask Custom Question

See attached Word Document. I have provided example of charts.

I will use this problems for additional exercises as well as guide for correctness.

Thank you

Purchase this Solution

Solution provided by:
Education
  • BE, Bangalore University, India
  • MS, University of Wisconsin-Madison
Recent Feedback
  • "Your explanation to the answers were very helpful."
  • "What does 1 and 0 means in the repair column?"
  • "Went through all of the formulas, excellent work! This really helped me!"
  • "try others as well please"
  • "Thank you, this helped a lot. I was not sure how to plug in those numbers to a formula. This was a great help. Now I have to figure out how to explain cost of capital is used in net present value analysis, and how cost of capital is used in net present value analysis. This stuff gets confusing."
Purchase this Solution


Free BrainMass Quizzes
Managing the Older Worker

This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce

Situational Leadership

This quiz will help you better understand Situational Leadership and its theories.

Operations Management

This quiz tests a student's knowledge about Operations Management

Learning Lean

This quiz will help you understand the basic concepts of Lean.

Introduction to Finance

This quiz test introductory finance topics.