Project Completion and Activity Time

This content was STOLEN from BrainMass.com - View the original, and get the solution, here!

You will be given a list of the activities of a project with completion time estimate for each activity. You will be asked to calculate 7 questions.
(a) Calculate the expected duration of each activity. Also, calculate the expected duration of each path.
(b) Calculate the variance of each activity and variance of each path. Also, calculate the standard
deviation of each activity and the standard deviation of each path.
(c) Identify the critical path(s) (based on the expected durations).
(d) What is the probability that the project can be completed within 49 weeks? What is the probability
that the project will NOT be completed within 49 weeks?
(e) What is the probability that the project will require 47 weeks or more? What is the probability that
the project will NOT require more than 47 weeks?
(f) What is the probability that the project will be completed between 45 and 50 weeks?

PLEASE SEE ATTACHED EXCEL SHEET FOR THE DATA.

© BrainMass Inc. brainmass.com September 19, 2018, 4:46 pm ad1c9bdddf - https://brainmass.com/business/project-management/project-completion-activity-time-519880

Attachments

Solution Preview

See the attached file.

activity mean (expected duration) variance standard ...

Solution Summary

The solution discusses project completion and activity time.