Project Completion Time
Not what you're looking for?
Consider the network in the attachment.
1. Compute the earliest start time (ES) of activity G using a forward pass.
2. Compute the project completion time.
3. Compute the latest finish time (LF) of activity B using a backward pass.
Purchase this Solution
Solution Summary
Solution shows step-by-step computation along with relevant explanation in each case.
Solution Preview
Let Ei represent the earliest start time for activity i such that all its preceding activities have been finished, and Ti be the activity completion time associated with activity i.
1. Using forward pass we can compute the earliest start time (ES) of activity G as below.
EA = 0
EC = EA + TA = 0 + 2 = 2
ED = EA + TA = 0 + 2 = 2
EE = EC + TC = 2 + 4 = 6
EG = Max[ED + ...
Purchase this Solution
Free BrainMass Quizzes
Transformational Leadership
This quiz covers the topic of transformational leadership. Specifically, this quiz covers the theories proposed by James MacGregor Burns and Bernard Bass. Students familiar with transformational leadership should easily be able to answer the questions detailed below.
Basic Social Media Concepts
The quiz will test your knowledge on basic social media concepts.
Cost Concepts: Analyzing Costs in Managerial Accounting
This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Business Ethics Awareness Strategy
This quiz is designed to assess your current ability for determining the characteristics of ethical behavior. It is essential that leaders, managers, and employees are able to distinguish between positive and negative ethical behavior. The quicker you assess a person's ethical tendency, the awareness empowers you to develop a strategy on how to interact with them.